Pool Renovation UPDATE & FAQ

Click here to see a pdf of the original plans for the pool renovation. We are still in the process of permits with the city. Once the plans become final, we will add them to the page.

Pool Renovation FAQ

Q: Why has the pool renovation been delayed?
A: The construction for the pool has been delayed due to the lengthy city permit process.

Q: What is the next step?
A: Once we resubmit the plans with the minor modifications, the city will review the plans and get back to us with the final permits.

Q: When will we have the final permits and plan for the pool renovation?
A: Around the end of March we hope to have final plans and permits.

Q: Who is in charge of the renovation?
A: The board HOA President is heading up the project along with the Architect, ADA Consultants and Doug Carey Construction.

Q: When is the anticipated start date for construction?
A: The anticipated start date for construction will be the close of the pool season in September.

Q: Is the job on budget?
A: Up to this point, yes the job is on budget.

Q: What will be done before the swim season begins?
A: Before swim season starts the following will be done:

  • tree removal – DONE
  • upgrade exterior lights to LEDs
  • add 2 flood lights to canopy by bathroom to be used for events only
  • replace 3 lights in pump room
  • switch light switches in bathroom to motion lights rather than the timer
  • pool furniture upgrade (7 tables, 28 chairs, and 4 chaise lounge chairs)
  • new clock
  • pool pump replacement to a 5 HP pump, replacing the two smaller pumps
  • replace the doors on the pump room – need a fiber glass vented door due to the sun and chemical usage and for security reasons

For more detailed information, please refer to our meeting minutes from March 14.